Component Project 1 under the Khanh Hoa – Buon Ma Thuot Expressway Construction Project (Phase 1)

PROJECT OVERVIEW
- Location: Ninh Hoa Ward, Khanh Hoa Province
-
Type, Grade of works: Grade I Transportation Works
-
Total Investment: VND 2,176 billion
-
Project Owner: Project Management Board for Construction Investment of Agriculture and Transport Works of Khanh Hoa Province
-
Contract: No. 26/2023/HDTV
Project details
-
Goals and benefits
-
Highlights
-
Progress & Results
-
Participating experts
-
Design duration
The Road Network Planning for the 2021–2030 period, with a vision to 2050, approved by the Prime Minister in Decision No. 1454/QD-TTg dated September 1, 2021:
- Route: The Khanh Hoa – Buon Ma Thuot expressway has a length of approximately 130 km.
- Alignment: Starting point at Van Phong Port, Khanh Hoa; ending point at the North-South Expressway (West), Buon Ma Thuot City, Dak Lak.
- Planned scale: 4 lanes.
- Investment timeline: Before 2030.
Construction Investment: Component Project 1 under the Khanh Hoa – Buon Ma Thuot Expressway Project (Phase 1), section Km0+000 – Km32+000 passing through Ninh Hoa Town, Khanh Hoa Province.
Connectivity: Connects vital traffic axes: National Highway 1 (QL1), National Highway 26B (QL26B), Van Phong – Nha Trang Expressway (CT.01), and National Highway 26 (QL26), creating a linkage axis from the South Van Phong Port area to the Central Highlands.
Benefits (derived from expressway characteristics & connection location):
Contribute to socio-economic development and ensure national defense and security for the South Central Coast and Central Highlands regions.
Reduce travel time and transport costs between Khanh Hoa and the Central Highlands.
Increase cargo circulation capacity for the South Van Phong Port area.
Project Scale & Technical Standards
- Grade-100 Expressway, Design speed ($V_{des}$) = 100 km/h, Grade I road transport project.
- Route length: Approximately 31.5 km, passing through 07 communes and 01 ward of Ninh Hoa Town.
- Final stage: 4 lanes, Roadbed width ($B_{bed}$) = 24.75 m; Phased investment stage: 4 lanes, $B_{bed}$ = 17.0 m; specifically, the section Km0 – Km8+500 is fully invested/completed in Phase 1.
Key Interchanges
- Start-point interchange with National Highway 1 (NH1) & NH26B: Roundabout type.
- Interchange with Van Phong – Nha Trang Expressway (CT.01): Full cloverleaf type.
- Interchange with NH26: Diamond type (Expressway overpasses NH26); Phase 1 comprises the construction of a through-traffic flyover with capital provision to complete the interchange before 2026.
Route Structures (Major Scale)
- 21 bridges: 18 bridges on the expressway alignment, 2 overpasses, and 1 bridge on the frontage road; including several major bridges such as Song Lop, Song Cai, Hon Lai, Km26, Km29, Km30 utilizing Prestressed Reinforced Concrete (PRC) Super-T girders.
- 29 frontage road sections with a total length of ~17.9 km; 15 residential underpasses; 08 retaining wall sections of various types.
- Large-scale drainage system: 175 cross culverts (pipe & box culverts), numerous longitudinal ditches, berm ditches, interceptor ditches, and reinstatement of 11 irrigation canal locations.
Safety & Environmental Infrastructure
Protective fencing, guardrails, and noise barriers at densely populated sections (Km0+000 – Km1+200, Km3+800 – Km4+000) in accordance with the approved EIA (Environmental Impact Assessment).
ITS infrastructure provision (cable manholes, cable conduits, pole foundations).
Lighting at main interchanges using 100–220W LED lights, arranged according to specific roadbed widths.
Current Results (As of Decision 602/QD-DAGT dated June 2, 2023)
-
Survey Task and Technical Design (T.D) Preparation: Approved via Decision 313/QD-DAGT dated March 24, 2023.
-
Survey Documents (Technical Design Stage): Acceptance approved via Document 490/DAGT-BDH dated May 6, 2023.
-
Appraisal: The Vietnam Expressway Authority appraised the Technical Design and Cost Estimates via Document 552/CDCTVN-QLXDKT dated May 31, 2023.
-
Verification: The Institute of Transport Science and Technology (ITST) verified the Technical Design via Report 1215/VKHCN-KHDA dated June 1, 2023.
-
Final Approval: On June 2, 2023, the Director of Khanh Hoa Transport Project Management Unit (PMU) issued Decision No. 602/QD-DAGT approving the Technical Design documents for Component Project 1 (Km0 – Km32).
Contractors & Personnel
-
Survey & Construction Design Contractor (Design Consultant): Truong Son Consultancy JSC – T27 Consultancy JSC Joint Venture.
-
Design Verification Contractor (Verification Consultant): Institute of Transport Science and Technology (ITST) – Institute of Construction Economics Joint Venture.
-
Personnel:
-
07 Lead Engineers.
-
43 Technical Staff.
-
Project Timeline
-
March 24, 2023: The PMU issued Decision No. 313/QD-DAGT approving the survey task and the preparation of the Technical Design (T.D).
-
May 6, 2023: Completion and acceptance of the survey results report for the Technical Design.
-
May 31, 2023 – June 1, 2023: Appraisal by the Vietnam Expressway Authority; Verification of the Technical Design by the Institute of Transport Science and Technology (ITST).
-
June 2, 2023: The PMU issued Decision No. 602/QD-DAGT approving the Technical Design.
Implementation Duration
-
Project Formulation Phase (Feasibility Study): 90 days.
-
Technical Design Phase: 60 days.
-
Working Drawing Design Phase: In accordance with the construction schedule.