Subproject of investment and construction of the Cam Lam – Vinh Hao section – Item: Interchange 709

image

PROJECT OVERVIEW

    • Location: Nhi Ha Commune, Thuan Nam District, Ninh Thuan Province.

    • Type and Grade of Work: Grade II Traffic Infrastructure Project (or Grade II Transport Work).

    • Contract Value: VND 1,522,583,000 (Vietnamese Dong).

    • Investment Owner: Project Management Unit 85 (PMU 85).

    • Contract: No. HD2500117604_2507291020.

Project details

  • Goals and benefits
  • Highlights
  • Progress & Results
  • Participating experts
  • Design duration

Construction Supervision: Ensure the quality, quantity of work, schedule/progress, occupational safety, and environmental hygiene for Package No. 16 (Construction of the Thuan Nam Interchange).

Transport Connectivity: Investment and complete construction of the Thuan Nam Interchange, connecting with Provincial Road DT.709, and linking with the access road connecting the North-South Expressway to National Highway 1 and the Ca Na General Seaport.

Key Technical Components/Items:

  • Main Expressway Alignment: The approved scale/scope shall be maintained.
  • Connecting Ramps/Branches: Subgrade width of 8m, pavement width of 6m.
  • Toll Station: Electronic Toll Collection (ETC) – Non-stop tolling system; 02 free-flow entry lanes, 02 exit lanes with barriers, integrated with an ITS (Intelligent Transportation System) (CCTV, VDS, VMS, etc.).
  • Contract Type: Lump-sum contract.

Joint Venture Work Division:

Bridge & Tunnel Design Consulting Joint Stock Company (JSC): 15% of the value (Supervision of toll station equipment installation).

T27 Consulting Joint Stock Company (JSC): 85% of the value (Supervision of civil works construction and installation, excluding toll station equipment).

Contract Execution Period: Calculated from the Effective Date of the Contract until all parties have fulfilled their obligations.

Construction Schedule/Progress: According to the execution period of Package No. 16, which is 120 days.

Warranty Period: 12 months starting from the completion of the services.

Contract Signing Date: July 30, 2025.

5 Key Personnel: Including 1 Chief Supervision Consultant (Đỗ Văn Phong) and 4 Supervision Consultants.

4 Other Personnel: Support staff.

Total: 9 personnel mobilized.

Construction Phase: 120 days

Warranty Phase/Period: 12 months.