Expansion and Upgrading of the Traffic Intersection at the Dong Da – Hoa Lu 5-Way Junction Area, Quy Nhon City

PROJECT OVERVIEW
-
-
Location: Quy Nhon City – Binh Dinh Province
-
Project Classification: Group B
-
Total Investment: Approximately 513 billion VND
-
Project Owner: Project Management Unit for Traffic and Civil Works of Binh Dinh Province
-
Contract: No. 87/2025/HD-TVXD
-
Project details
-
Goals and benefits
-
Highlights
-
Progress & Results
-
Participating experts
-
Design duration
Contributing to the completion of the Binh Dinh Provincial Master Plan for the 2021–2030 period, with a vision to 2050, approved by the Prime Minister in Decision No. 1619/QD-TTg dated December 14, 2023.
The realization of the project will address traffic congestion at the intersection area, aligning with its position as a strategic gateway to and from Quy Nhon city center.
Consultancy services for surveying and preparing the Feasibility Study Report for construction investment of the project: ‘Expansion and Upgrading of the Traffic Intersection at the Dong Da – Hoa Lu 5-Way Junction Area, Quy Nhon City.
Application of BIM in surveying and design to model existing conditions, analyze, and select optimal solutions, thereby enhancing traffic safety, reducing congestion, and completing the urban transport infrastructure.
Establishing a synchronized digital database for the subsequent phases of design – construction – operation management (Common Data Environment – CDE, 3D models, digital documentation).
Specialized consultancy contract for surveying, preparing the Feasibility Study Report (FSR), and Building Information Modeling (BIM), including a BIM Execution Plan (BEP) and a detailed list of BIM deliverables.
Establishment of a Common Data Environment (CDE) to manage and share project data.
3D modeling of existing conditions, traffic models, technical infrastructure, and architecture to facilitate the analysis and selection of intersection design options.
Mobilization of a consortium comprising two consulting firms (T27 Consultancy JSC and Viet Long Technology Development Co., Ltd.) with a large team of experts, featuring clearly defined roles and implementation schedules.
Contract Implementation Period (including surveying, preparing the FSR, and BIM): 120 days from the contract effective date, in accordance with Article 25.
The detailed schedule is divided into milestones:
-
Commencement Date: April 14, 2025.
-
The duration for surveying tasks, preparation of the Feasibility Study Report, and BIM modeling is specifically stipulated in Article 25 and the Contract Schedule Appendix.
Key Results/Deliverables (Excerpts from Articles 11, 12, and the Appendix):
-
Construction Survey Report.
-
Construction Investment Feasibility Study Report (FSR).
-
BIM Execution Plan (BEP) and project BIM workflow system.
-
BIM Models: Existing conditions model, traffic model, traffic safety, technical infrastructure, architecture, etc.
-
Drawing dossiers, digital documentation extracted from BIM models, and accompanying reports.
a total of 17 experts are mobilized for this consultancy package
The design duration (comprising surveying, preparation of the Feasibility Study Report, and BIM implementation for the Dong Da – Hoa Lu intersection) coincides with the consultancy contract implementation period: 120 days.
Some pictures of the project